"How can I compare the current plan against a specific baseline or 2
different baselines to each other?"
I fielded this question earlier today and don't have an idea of best
practice. Whenever I'm interested in baselines, I simply put the
baseline column (start, finish, work, etc.) into a view. I usually use
the Gantt chart view. That has always been sufficient for me.
What is best/recommended practice?
Thanks!
Crook
different baselines to each other?"
I fielded this question earlier today and don't have an idea of best
practice. Whenever I'm interested in baselines, I simply put the
baseline column (start, finish, work, etc.) into a view. I usually use
the Gantt chart view. That has always been sufficient for me.
What is best/recommended practice?
Thanks!