Good day,
I looking set a FS relationship where the start is on the Xth date of the
following month.
Any suggestions would be appreciated.
Thanks in advance
 
R

Rod Gill

You can't do this with relationships. Your 2 options are:

1) create a calendar that you use only for this task with the Xth date
working only. Might as well just set a date.

2) use a VBA macro.
 
R

Richard

I've been working the VBA macro... hadn't thought of using a separate
calendar. That makes sense since the task is related to an external resource.
Thank you Rod, I appreciate the feedback.
 