Look at the Project Summary Report. (View > Reports, Overview). It
contains a section on Task status including:
Task not yet started
Tasks in progress
Tasks completed
Total tasks
Sorry, no, I don't believe so. You could certainly export simple task
data to excel on a weekly basis (task name, % complete) and then run a
CountIF in excel to count the number of complete and incomplete tasks.