Muddypaws said:
Can a report be created over 10 seperate projects? Like the basic
Summary Report that you can use in Report, Overview, Project Summary.
I can get them individually, great. But I need to see the overall
summary for all 10 projects, is this possible
Muddypaws,
It depends on the level of detail, but yes, it can be done. If all you
really need is schedule and cost information across the 10 projects you
can get that from the built-in Project Summary report by creating a
master file will all 10 projects inserted. To do that, first create a
new blank project file. Then go to Insert/Project and select all 10
projects. What you will end up with is a dynamically consolidated master
and you can either activate the Project Summary Task via
Tools/Options/View tab, or use the aforementioned built-in report. Be
advised that you will NOT get resource information using this approach
because there are no resources at the master level itself. All resources
are in each of the inserted subprojects. However, if you are using a
common resource pool file, you could run the report on the pool file to
get summary resource information.
If you want more detailed information and/or need resource data across
the 10 projects (in the absence of a common resource pool), you will
need to use VBA. If you do not have experience with Project VBA, fellow
MVP, Rod Gill has an excellent book on the subject. In it are several
examples for doing things like you want. For more information, see,
http://www.projectvbabook.com
Hope this helps,
John
Project MVP