gpappy said:
I want to create in Project pass/fail decision points which will loop back if
fail or go down different schedules depending upon the outcome. Can this be
done ion Project?
gpappy,
Project Managers face this kind of decision making every day. The
"normal" technique is a regular periodic review of the information
Project is providing followed by informed decisions to re-structure the
plan in order to achieve the desired outcome. Project provides the
information but it can't make the decisions - the manager has to so that.
However there are ways to automate plan re-structuring depending on a
set of defined criteria. The best way to implement this is through VBA.
Hope this helps.
John
Project MVP