Critical Path & Late Finish Dates

M

Michael Longdin

I have a strange situation where critical path indicators and the late finish
date are both showing different values for tasks depending on which user
opens the project file.

An example would be

Task A (duration 4 days)
Start: 02/07/08,
Finish: 08/07/08
Late Start: 06/08/08
Late Finish: 12/08/08
Critical: No

If another User opens the project (in either read/write or read only mode)
then the following shows. I think this has to be incorrect anyway as the the
Critical indicator would be showing Yes if the late finish date was the same
as the Late Finish date?

Start: 02/07/08,
Finish: 08/07/08
Late Start: 02/07/08
Late Finish: 08/07/08
Critical: No

We're using MS Project Server & MS Project Pro 2003

Can anyone explain why this happens?
 
Top