daily update: how to do?

G

ghitorni

In Project 2007, if a task is done just 25% on day 1, say February 1, how to
get to input daily progress? Do I get to see a 2nd Feb as the date too?
Please help. Thanks
 
J

Jan De Messemaeker

Hi,

In Task Usage View, right click on the grapgical half of the view, check
Actual Work.
If necessary adapt the timescale to show days as minor scale.
Now you can enter actual work on a daily basis.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
D

Dave

ghitorni said:
In Project 2007, if a task is done just 25% on day 1, say February 1, how to
get to input daily progress? Do I get to see a 2nd Feb as the date too?
Please help. Thanks

You have a number of options:
- Look at the update project options under Tools/Tracking
- Look at the update tasks options under Tools/Tracking
- You can enter actuals against the tasks under the resource usage or
task usage views
- You can over over the left hand edge of a task and drag a progress bar
along

You may find it useful to study the FAQ pages at:

http://project.mvps.org/faqs.htm
 
S

Steve House

There's a little trap entering % Complete to be aware of. That is, %
Complete refers to duration ONLY. % Work Complete and % Physical Complete
are different measures. So if your task is done 25% on Feb 1st with one day
of work, the task has to have been a 4 day duration task. If the 25%
represents work done on both 30 Jan and 01 Feb, then it is an 8 day duration
task, and so on. The trap is in using % Complete as an entry in the first
place because when you ask people how they're doing and they reply "I'm
halfway done" they're usually thinking in terms of either work or the actual
physical progress and not the time put in versus time required measure that
Project is based on. You'll get far better tracking of progress if you
solicit updates in the form of "How much time have you put in on it and how
much time do think you will need before it's done?" and let Project figure
out the percentages.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top