Dear all,

Working with MSProject'98, for a medium size company with around 3
projects executed simultaneously. Created Master by inserting al
individual projects as sub-project. Everything working fine as desire
except one thing where I need your advice.

We have created certain tables for different people to see th
information in desired formats, like Customer will see only activit
name, start & end date. Managers will see hours & resource names &
compl. in another table. Like these, there are 3 more customise
tables. We want each table to have its own formatted gantt chart wit
it. We are not able to associate the default gantt with the table.

Is it possible to have default gantt chart (formatted for that table
to open when we open the particular table in MSP98
 
D

davegb

Once you have the special Gantt and table created, save them as a
"View". When you want to see it that way, select your custome view.
 