We have a Project that in task usage View you can see the actual Work hours
in it's column, but whe move to the detail area & you make the project show
the Work & actual Hours NO numbers appear in any of the period slots.
 
M

Mike Glen

Hi Jose,

Welcome to this Microsoft Project newsgroup :)

I'm not fully sure I understand you, but I assume you're looking at the Task
Usage view and you have inserted a column for Actual Work. On right hand
side in the details time-scaled cells, right-click and select Actual Work.
Now select your task and click the Go-to button on the Standard toolbar.
Are you saying all the cells are empty?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
J

Jose Zayas

Yes, Indeed this is case. Wehave done this and the detailed info that is
supposed to be On right hand side in the details time-scaled cells is blank,
either for actual and work which are the selected items in this view. and yes
we have verified that the font color is NOT WHITE. The interesting thing is
that the actual work and work are shown in the left columns.
 
M

Mike Glen

Hi Jose,

Assuming you have assigned resources to the tasks, I can only suspect
corruption. We need to discover whether your project is at fault, whether
it is Project at fault, or whether it's your PC. Does the symptom occur
with other projects on this PC? Does it occur with this project on other
PCs? Does it occur with other projects on other PCs?

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
J

Jose Zayas

We are using a Terminal Server to run Our MSProject Server, therefore
whenever you log on you will see the same results, different users have the
same results with the project in question. Then the only explanation must be
as you indicate is corruption of the Schedule of this project.

Thanks for you assistance!!!!
 
M

Mike Glen

Hi Jose,

That's different! Try posting on the server newsgroup. Please see FAQ
Item: 24. Project Newsgroups. FAQs, companion products and other useful
Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top