P
project-guy
Our program operates in an environment where we have 4 Project files with
links between them. In addition, we have 2 Consolidated files, 1 for every 2
of the Project files. All of these files are stored in a common folder on
the network.
When we display the external links, we see as many as 8 links to any one of
internal task in a Project file. When you examine the predecessor or
succesor fields in the split screen, we see that half of the links are
duplicated exactly. The other half of the links refer to external links
which do not exist ( the task ID's differ by 1 ID number from the actual task
number in the external Project file.
In one of my files, I had upwards of 100 external links defined ( links I
wanted to include). These have translated to 600-800 external tasks in my
project file, certainly contributing to a file size issue, not to mention the
possibility of incorrect transfer of dates to the dependant internal tasks
(dependancy dates also may differ on the duplicates).
Does anyone have any explanation for this and do you have a cure to
eliminate the invalid duplicate external links? i havre searched the
Discussion Group and did not find any one mentioning this type of issue
before.
links between them. In addition, we have 2 Consolidated files, 1 for every 2
of the Project files. All of these files are stored in a common folder on
the network.
When we display the external links, we see as many as 8 links to any one of
internal task in a Project file. When you examine the predecessor or
succesor fields in the split screen, we see that half of the links are
duplicated exactly. The other half of the links refer to external links
which do not exist ( the task ID's differ by 1 ID number from the actual task
number in the external Project file.
In one of my files, I had upwards of 100 external links defined ( links I
wanted to include). These have translated to 600-800 external tasks in my
project file, certainly contributing to a file size issue, not to mention the
possibility of incorrect transfer of dates to the dependant internal tasks
(dependancy dates also may differ on the duplicates).
Does anyone have any explanation for this and do you have a cure to
eliminate the invalid duplicate external links? i havre searched the
Discussion Group and did not find any one mentioning this type of issue
before.