Duration Changes when project pasted into Master Project.

A

adamtanderson

I have been using the Project 2007 Beta. I have been using a master
project and pasting sub projects into it. I have been having problems
with one of the sub projects. The duratin times differ from the sub
project and the same projet when viewed in the master project. The
duration will be listed as 1 day in the subproject but 1.88 days when
viewed in the masterproject. If I change the duration in the master
project to 1 day then the duration changes to .053 days in the sub
project. I am only having this problem with one subproject
 
A

adamtanderson

I have been using the Project 2007 Beta. I have been using a master
project and pasting sub projects into it. I have been having problems
with one of the sub projects. The duratin times differ from the sub
project and the same projet when viewed in the master project. The
duration will be listed as 1 day in the subproject but 1.88 days when
viewed in the masterproject. If I change the duration in the master
project to 1 day then the duration changes to .053 days in the sub
project. I am only having this problem with one subproject

I finally figured out what I had done. I had changed the default hours
per day and hours per week so it was giving me trouble when I wasw
pasting it into the master project.
 
J

Jan De Messemaeker

Hi,

In the subproject, a "day" is defined differently.
Tools, Options, Calendar, make it the same "day" as in the other ones
HTH
 