adamtanderson
I have been using the Project 2007 Beta. I have been using a master
project and pasting sub projects into it. I have been having problems
with one of the sub projects. The duratin times differ from the sub
project and the same projet when viewed in the master project. The
duration will be listed as 1 day in the subproject but 1.88 days when
viewed in the masterproject. If I change the duration in the master
project to 1 day then the duration changes to .053 days in the sub
project. I am only having this problem with one subproject