Example of a fixed work task

N

Nada_Wolf

Does anyone have a good example for each kind of task: fixed duration, fixed
unit, fixed work? Especially interested in examples showing the difference
between fixed unit tasks and fixed work tasks.
 
J

JulieD

Hi

in my book these don't directly relate to discrete tasks ... more a method
of how you want Project to react if you make a change ...
but here goes ....

fixed duration - a meeting ... doesn't matter how many people you throw at a
meeting it will always get longer rather than shorter :) ... seriously, a 1
hr meeting is a 1 hr meeting regardless of the number of people attending

fixed unit - default type ...

fixed work - if i know that it is going to take 10 man-hours and i want
project to tell me how many resources i need to complete the work in a given
duration i will use this task type.
 