All,
Is there a way to tell MS Project to "refresh" itself after putting in
large amounts of data? By refresh, I specifically mean to recalculate
all calendar dates based on the predecessors, successors and durations.
MS Project is supposed to do this automatically, but I've seen a few
cases where it doesn't. Being able to prompt MS Project to recalculate
all in the manner described above would be helpful.
v/r,
Mike Van, PMP