F
First Time User
My question is related to setting up projects and subtiers within that
project. I have used Timberline, but not Project so I don't really know
where to start.
I am trying to setup up 6 different projects within one Master Plan. Within
each of those projects I need cateories such as soft costs, indirect,
construction etc. Lastly, I need multiple costs codes within each of those
categories I want to be able to print reports at each of those levels.
Basically having reports that summarize cost information for the entire
project all the way down to very detailed information by cost code within
groups within projects within the overall master project.
Can anyone tell me if this is possible in project and how to do this? Or
where to get good detailed information on this type of setup.
Thank you.
project. I have used Timberline, but not Project so I don't really know
where to start.
I am trying to setup up 6 different projects within one Master Plan. Within
each of those projects I need cateories such as soft costs, indirect,
construction etc. Lastly, I need multiple costs codes within each of those
categories I want to be able to print reports at each of those levels.
Basically having reports that summarize cost information for the entire
project all the way down to very detailed information by cost code within
groups within projects within the overall master project.
Can anyone tell me if this is possible in project and how to do this? Or
where to get good detailed information on this type of setup.
Thank you.