W
wendyB
Hi
I am troubleshooting a plan that has been developed in MS Project 2000
(about 2000 lines).
Among the issues is one where tasks which have been scheduled with a Finish
No Later Than constraint, have finish dates that are earlier than their
predecessors (FS relationship) finish dates. A simplistic illustration of an
example:
1. Excavation Start Mar7, Finish Mar19, Constraint: ASAP
2. Pour concrete slab Start Mar15, Finish Mar17, Contsraint: FNLT Mar 18
Predecessor: 1(SF)
There are many such instances within the schedule which has been touched by
many people, in a shared environment where MS Project is deployed standalone.
There are no indicators to show such conflicts and I'm not sure whether this
is a limitation of 2000 or whether the issue has occured because the
scheduling alerts were disregarded when they did pop up. Can anyone shed
some light on this? In any case, I'd be interested to know whether 2002/3 or
Enteprise would overcome such an issue.
I am troubleshooting a plan that has been developed in MS Project 2000
(about 2000 lines).
Among the issues is one where tasks which have been scheduled with a Finish
No Later Than constraint, have finish dates that are earlier than their
predecessors (FS relationship) finish dates. A simplistic illustration of an
example:
1. Excavation Start Mar7, Finish Mar19, Constraint: ASAP
2. Pour concrete slab Start Mar15, Finish Mar17, Contsraint: FNLT Mar 18
Predecessor: 1(SF)
There are many such instances within the schedule which has been touched by
many people, in a shared environment where MS Project is deployed standalone.
There are no indicators to show such conflicts and I'm not sure whether this
is a limitation of 2000 or whether the issue has occured because the
scheduling alerts were disregarded when they did pop up. Can anyone shed
some light on this? In any case, I'd be interested to know whether 2002/3 or
Enteprise would overcome such an issue.