Hi Pooja,
Thanks for the information. What I understand you are doing is using a text
field referencing the % complete field. I did note some strange behavior
when using the graphic indicators in a Text field, but as I noted before,
all seems to work as required when placing the graphic indicators in a
*Number* field. Again, I did a quick test: I added the Number1 field to a
table and set the formula equal to the % complete. Then used the graphic
indicator values I listed in my previous post and all worked well.
But based upon the comment about wanting zero % complete to show red only if
the task is "behind us" leads me to ask yet another question:
On the surface it appears you only want to show graphic indicators based
solely on % complete, but wouldn't you want to have that % complete be
compared against the % complete you *should* be as of the status date?
Project has two fields that display information relating to % complete as of
the status date, the Status Field and the Status Indicator field.
The Status field takes into account not only the % complete of the task as
entered by the user, but also looks at where the task should be in relation
to the baseline information. The status field has 4 choices: tasks that are
100% complete show as "Complete". Tasks that are scheduled to start in the
future, show "Future Task". Tasks that are late (their % complete is less
than where it should be) show "Late", and tasks that are progressing on
schedule show "On Schedule".
The Status Indicator field has indicators for all of the options in the
Status field except for "Future Tasks" - they show no indicator.
It looks as though John has partially answered your question about the
Resource Graph. When you comment below that a problem with print preview is
only happening in the current file, but others look fine, it sounds as
though there is a problem with the current file. It is possible the file
has become corrupt. See FAQ #43 at the URL below for a possible fix.
http://project.mvps.org/faqs.htm
I hope this helps. If you would like additional information about setting
up custom graphic indicators for the Status field, let us know. Keep us
posted on how things progress.
Julie