I'm trying to calculate EV in a WBS project plan that I've already
completed.
Do I have to save my baseline in order for the EVM table to
calculate???
I've bought 3 books and no where does it give you a step by step
breakdown of how to actually make the EV table work.

Can someone offer a step by step take on how I should approach this or
a website or publication in which I can get a better understanding.


Ms. Conquest - Dept. Homeland Security
 
S

srs76

Thank you, that was informative, but I'm looking for info as to how to
feed MS Project information necessary to create a EVM table i.e. -
resouces, budget, etc.
 
S

srs76

I'm looking for info as to how to feed MS Project information necessary
to create a EVM table i.e. - resouces, budget, etc.

Ms. Conquest - Dept. Homeland Security
 
J

JulieS

Hi srs67,

In order to generate earned value data in Project you will need:
Tasks
Resources with Standard Rates and Overtime Rates (if you intend to
assign OT)
Resources assigned to the Tasks
Baseline
Tracking Data (Actual Work, Remaining Work, etc)

I hope this helps. Let us know how you get along.

Julie
 