How do I format work hours to eliminate tenths & hundreths?

When work is spread across several time periods, Project breaks that up
according to a schedule. The spread and sometime the sum of individual
resource hours results in partial hours, depicted typically in hundreths. Is
there any way to display hours as units, like $. i.e. no change and rounded
to the nearest unit?
 
D

Dale Howard [MVP]

jwhj --

There's no way to set the precision for the any field related to Work, the
way that you can set the precision for Costs. Because Microsoft Project
tracks Work at the 1 minute level, it is very precise when converting the
Work to hours. Hope this helps.
 
J

jwhj

Thanks; I was afraid of that. The only way I've been able to do it is to put
the hours in the month in the task usage view. It seems the "display" could
be units like dollars for appearances sake if nothing else.
jwhj
 