How do I add/modify columns in task view of Project web access?

B

Brian_of_WG

Currently in our application task owners update their "% complete" in the
"view my tasks" screen. To help implement an earned value analysis approach,
I would like for a task owner to be able to enter both actual work (in
hours), and % complete. The % percent complete most likely will not be the
same as the actual work divided by scheduled work, but rather an estimate
based on the current situation and experience.
For example, a task owner may have just completed 8 hours of work on a task
scheduled for 16 total hours. However, if problems occured, the task may
actually only be 20% complete, not 50% as Project would automatically
calculate. I would like the task owner to be able to enter 8 hours actual
work completed AND 20% work completed.
 
D

Dale Howard [MVP]

Brian --

Please do not cross-post your questions. We read all the Project
newsgroups, and I already answered your question in the
microsoft.public.project.server newsgroup.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top