How do I link recurring subtasks in Project

T

twheat

An example would be publishing a monthly newsletter with recurring draft,
review, edit and publish tasks for a 1 year period.
 
J

John

twheat said:
An example would be publishing a monthly newsletter with recurring draft,
review, edit and publish tasks for a 1 year period.

twheat,
I guess I don't understand the problem. Just add the appropriate
predecessors to each task in the recurring chain.

John
Project MVP
 