Joe
What’s the best way to handle reduced scope in terms of baselined project
plan? I have a plan that is baselined and after a few months of tracking
actuals and reporting EVA to mgmt, it was decided to defer a specific
functionality for another release sometime next year (This deferred scope
with be another project plan later on).
What’s the best way to remove the deferred portion without re-baselining the
entire plan? I don’t want the SPI and CPI to go back to 1.0; I just want to
delete the one section from the baseline and continue with the rest of the
project.
Any ideas or thoughts?
plan? I have a plan that is baselined and after a few months of tracking
actuals and reporting EVA to mgmt, it was decided to defer a specific
functionality for another release sometime next year (This deferred scope
with be another project plan later on).
What’s the best way to remove the deferred portion without re-baselining the
entire plan? I don’t want the SPI and CPI to go back to 1.0; I just want to
delete the one section from the baseline and continue with the rest of the
project.
Any ideas or thoughts?