How do I save a customized MS Project Report?

R

Rod Gill

Hi,

To save any customized view, report, table etc, use Tools, Organizer to copy
it to the Global.Mpt file. This will also make the view available to all
your projects.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
R

Robert

Please be more specific..

You can save a customised report by saving your
project!!! If you wish for it to be present in new
projects then you need to save it in your global.mpt

To do this, open the project with the desired report.
Choose Tools/Organizer/reports tab. Mark the report in
the "project" window, and copy it into the "global"
window, then close.

New projects will now include your report template!!

Is this what you were after???

Regards
Robert
 