You can set both the beginning and ending dates when you use the File |
Print menu option. In the Timescale section select the Dates radio button and
then select your From and To dates from the drop down dialogues.
My apologies! I was thinking about printing the Gantt chart, not a report.
To filter a report, you would need to create a custom filter that could then
be applied to your report via the Edit option. You may want to have a look at
several of the standard reports that are shipped with MS Project to see how
the date filters work, as you can set up a prompt ("Date"?) to request input
of the date when you run the report, or you could hard-code the date in the
filter.
Thanks Don... we were on the same page I was talking about Gantt charts
but typed reports. Thanks again your directions to File, Print was what
I was looking for...