how do you add %complete progress line to summary bars?

J

Jason

i've created a master schedule. I've changed the bars from roll-up task bar
to regular summary bars. Now, I need to show the %comple progress line on
these bars. The master schedule i was using with version 2000 had it done
automatically. how can i do it now with 2007? please help. need answer ASAP.
 
J

Jim Aksel

Format/Bar Styles....
Change the summary bar to something other than black it appears you have
done it.
Now, create a new line.

Name: Progress or progress
Appearance: Make same as other progress lines
Show For...Tasks: Summary
Row:1
From: Actual Start
Tl: Complete Through

Click OK
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
J

Jason

Thank you so much Jim. I have this master schedule due tomorrow and you saved
me :) whewww. thanks again!!!
 
J

Jim Aksel

Gee, can I bill you? (hee hee).
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top