How do you remove a subproject from a master project?

T

Todd Olson

I am trying to organize a group of independant projects in one location for
me to monitor. I would like to be able to remove projects as they are
completed so I have a running list of active projects. For some reason I
cannot remove subprojects. I have tried removing the link (task
information, Advance Tab, clear check from Link to project:), then deleting
the task, but this does not delete the task line, only the reference to the
other project.

Any suggestions. (Project Standard 2003)
 
P

Project Slave

Just press the delete key on the field in the master project Gantt chart
view. On the prompt window, select delete the <file> and its subtasks.
 