T
Todd
Let me give an example, I have a proj with task1, subtask11, subtask 12 and
task2. Also, let task1 be a development task with subtask11 and subtask12 as
its child tasks, let task2 be a UI design task. Now I have a development lead
named Bob in charge of task1, also I have Cindy and Daniel to work on
subtask11 and subtask12 respectively. Now I want to authorize Bob to verify
if subtask11 and subtask12 are truely finished. By default, only PM has the
authority to approve the task update, right? How can I authorize Bob to
approve the update of subtask11 and subtask12 but not task2?
task2. Also, let task1 be a development task with subtask11 and subtask12 as
its child tasks, let task2 be a UI design task. Now I have a development lead
named Bob in charge of task1, also I have Cindy and Daniel to work on
subtask11 and subtask12 respectively. Now I want to authorize Bob to verify
if subtask11 and subtask12 are truely finished. By default, only PM has the
authority to approve the task update, right? How can I authorize Bob to
approve the update of subtask11 and subtask12 but not task2?