PaoloKramer
Hi,
I'm currently working on a civil engineering project in a continental
climate, where the weather can prevent large scale open-air works for up to 5
months per year, while other works such as tunnelling or fitting out of
already constructed buildings, etc, can continue.
I need to be able to create a block in the calendar for these five months
and be able to specify whether a particular task can be carried out during
these periods. Is this possible?? I think perhaps it is too complicated for
poor ol'Project....
Thanks - Paul
I'm currently working on a civil engineering project in a continental
climate, where the weather can prevent large scale open-air works for up to 5
months per year, while other works such as tunnelling or fitting out of
already constructed buildings, etc, can continue.
I need to be able to create a block in the calendar for these five months
and be able to specify whether a particular task can be carried out during
these periods. Is this possible?? I think perhaps it is too complicated for
poor ol'Project....
Thanks - Paul