How to resource appropriately

T

Turbo Adam

I'm new to using MS Project so forgive any blatant ignorance...

I work at an engineering company where we do a lot of compute
analysis.
I've been tasked with creating a schedule that will determine when w
will
have computer down-time. The resources that will constrain the schedul
are
licenses for our analysis software.

Each analysis we perform has 3 parts; pre-solver, solver and
post-processing. Each of those parts will run for a designated amoun
of
time and requires the use of the appropriate license. We have two o
each
type of license available, (I could run 2 solvers simultaneously fo
example).

How on Earth do I set the license in question as a resource and sa
that it
can only be used in 2 tasks simultaneously and that the remaining task
will
be have to be pushed out accordingly?

Many thanks to anyone with advice
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top