Jessaqua said:
We need to schedule some short tasks over a longer span of time, for instance
an hour long conference call that will need to happen within a three day
period. Can Project do this?
Jessaqua,
What you are describing is the basic difference between task duration
and task effort. Both fields are normally expressed in hours or days but
they represent totally different concepts. Task duration is the time
span during which the task is performed. In your case, that is 3 days.
Effort is captured by the Work field and represents the time one or more
resources will actually spend accomplishing the task. In your case that
is 1 hour.
To set this up in Project, select the task and go to Project/Task
Information/Advanced tab. Set the Task type to "Fixed Duration" with the
"effort driven" option not selected. Enter 3 days in the Duration field
for the task. In the Resource Names field, select those resources that
will be involved in the conference call and in the Work field, (you may
need to add this field as a column in the view), enter 1 hour. That will
give you a 1 hour call that can take place at anytime during the 3 day
period.
Hope this helps.
John
Project MVP