Hi,

Looking at the SDK you need the Statusing web service but I'm afraid I don't
have any sample code. I always update directly using Project and VBA. There
is a little help at:
http://blogs.msdn.com/brismith/archive/2007/02/02/adding-timephased-actual-work-through-the-psi.aspx

More information with a little sample code starting at:
http://msdn2.microsoft.com/en-us/library/websvcstatusing.aspx

I assume you are NZ based? Where about? I'm near Matakana about an hour
north of Auckland.

--

Rod Gill
Project MVP

Project VBA Book, for details visit:
http://www.projectvbabook.com