Importing the holiday calender from MS Outlook '03 into MS Project

D

Dale Howard [MVP]

Bruce --

It can't be done using the default features of Microsoft Project. You must
manually enter company holidays on your calendar(s) in Microsoft Project
using Tools - Change Working Time. Sorry.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com