hi,
thanx to Dale Howard, i was able to implement the stoplight function. now i
have another question regarding another issue with Project. i was wondering
if i cud add conditions for specific tasks so the color goes red, green, etc.
for example say i want a task to appear RED after 6 days of being active,
then i want another task in the same project to appear RED after 10 days of
being active. here when i say "being active" i mean that the task has a
deadline of 6 days and on the 7th day the task shud have a RED STOP light in
a column that i designate it. thanx for the help in advance...if the Q isnt
clear....please post a comment and i will try to clarify.
schemr
thanx to Dale Howard, i was able to implement the stoplight function. now i
have another question regarding another issue with Project. i was wondering
if i cud add conditions for specific tasks so the color goes red, green, etc.
for example say i want a task to appear RED after 6 days of being active,
then i want another task in the same project to appear RED after 10 days of
being active. here when i say "being active" i mean that the task has a
deadline of 6 days and on the 7th day the task shud have a RED STOP light in
a column that i designate it. thanx for the help in advance...if the Q isnt
clear....please post a comment and i will try to clarify.
schemr