P
Peter Rooney
This is a bit messy, but here goes.
I had a mini project within my plan, including the following tasks:
Task 1 Start Tuesday 26/04/05 09:00 End Friday 29/04/05 17:30 50% comp
Task 2 Start Tuesday 03 05/05 09:00 End Thursday 05/05/05 17:30 50% comp
Task 3 Start Friday 06/05/05 09:00End End Tuesday 10/05/05 17:30 50% comp
Task 4 Start Wednesday 11/05/05 09:00 End Friday 13/05/05 17:30 0% comp
Task 5 Start Monday 16/05/05 09:00 End Wednesday 18/05/05 17:30 50% comp
Task 6 Start Thursday 19/05/05 09:00 End Monday 23/05/05 17:30 0% comp
Task 7 Start Tuesday 24/05/05 09:00 End Thursday 26/05/05 17:30 50% comp
All tasks are linked and all are Start As Soon As Possibles.
I'm now trying to reduce the working day for the single resource concerned
to 5.5 hours from the current 7.5. So, I did a blanket change on her
calendar, changing the working pattern from 09:00-13:00 and 14:00-17:30 to
09:00-13:00 and 14:00 to 15:30.
The purpose of the exercise is to see by how much the project end date will
be pushed out.
Now, for the corresponding tasks, I get the following:
Task 1 Start Tuesday 26/04/05 09:00 End Friday 29/04/05 17:30 50% comp
Task 2 Start Tuesday 03 05/05 09:00 End Thursday 06/05/05 11:00 50% comp
Task 3 Start Friday 06/05/05 09:00 End Wednesday 11/05/05 13:30 50% comp
Task 4 Start Wednesday 11/05/05 14:00 End Tuesday 17/05/05 14:30 0% comp
Task 5 Start Monday 16/05/05 09:00 End Thursday 18/05/05 14:45 50% comp
Task 6 Start Thursday 19/05/05 14:45 End Wednesday 25/05/05 15:15 0% comp
Task 7 Start Tuesday 24/05/05 09:00 End Friday 27/05/05 15:30 50% comp
Original durations were 4, 3, 3, 3, 3, 3, 3
Modified durations are 4, 3, 2.73, 3, 2.73, 3, 2.73
Some of the changes I understand - some I don't - for instance, why have the
durations of tasks 3, 5 and 7 changed from 3 days to 2.73 days?
Is it something to do with the fact that they've been started - in that
case, why haven't 1 and 2 changed as well?
Whilst Tasks 2, 4 and 6 still add up to 22.5 hours, Task 5 now only adds up
to 21.25 hours, based on the start and end times shown (Mon, Tue & We @ 5.5
hours and Thu @ 4.75 hours), even though the Work for both after the changes
still shows as 22.5 hours - but 21.25 ISN'T 2.73 days of 5.5 hours' duration!
I know this is probably something really fundamental about Project that I
should understand, considering I've been working with it for 6 months, but,
sad to say, I don't. I just hope that someone out there will take a look at
how long it took me to get this in here and try to give me some basic
pointers
)
Thanks (B-I-G thanks) in advance
Pete
I had a mini project within my plan, including the following tasks:
Task 1 Start Tuesday 26/04/05 09:00 End Friday 29/04/05 17:30 50% comp
Task 2 Start Tuesday 03 05/05 09:00 End Thursday 05/05/05 17:30 50% comp
Task 3 Start Friday 06/05/05 09:00End End Tuesday 10/05/05 17:30 50% comp
Task 4 Start Wednesday 11/05/05 09:00 End Friday 13/05/05 17:30 0% comp
Task 5 Start Monday 16/05/05 09:00 End Wednesday 18/05/05 17:30 50% comp
Task 6 Start Thursday 19/05/05 09:00 End Monday 23/05/05 17:30 0% comp
Task 7 Start Tuesday 24/05/05 09:00 End Thursday 26/05/05 17:30 50% comp
All tasks are linked and all are Start As Soon As Possibles.
I'm now trying to reduce the working day for the single resource concerned
to 5.5 hours from the current 7.5. So, I did a blanket change on her
calendar, changing the working pattern from 09:00-13:00 and 14:00-17:30 to
09:00-13:00 and 14:00 to 15:30.
The purpose of the exercise is to see by how much the project end date will
be pushed out.
Now, for the corresponding tasks, I get the following:
Task 1 Start Tuesday 26/04/05 09:00 End Friday 29/04/05 17:30 50% comp
Task 2 Start Tuesday 03 05/05 09:00 End Thursday 06/05/05 11:00 50% comp
Task 3 Start Friday 06/05/05 09:00 End Wednesday 11/05/05 13:30 50% comp
Task 4 Start Wednesday 11/05/05 14:00 End Tuesday 17/05/05 14:30 0% comp
Task 5 Start Monday 16/05/05 09:00 End Thursday 18/05/05 14:45 50% comp
Task 6 Start Thursday 19/05/05 14:45 End Wednesday 25/05/05 15:15 0% comp
Task 7 Start Tuesday 24/05/05 09:00 End Friday 27/05/05 15:30 50% comp
Original durations were 4, 3, 3, 3, 3, 3, 3
Modified durations are 4, 3, 2.73, 3, 2.73, 3, 2.73
Some of the changes I understand - some I don't - for instance, why have the
durations of tasks 3, 5 and 7 changed from 3 days to 2.73 days?
Is it something to do with the fact that they've been started - in that
case, why haven't 1 and 2 changed as well?
Whilst Tasks 2, 4 and 6 still add up to 22.5 hours, Task 5 now only adds up
to 21.25 hours, based on the start and end times shown (Mon, Tue & We @ 5.5
hours and Thu @ 4.75 hours), even though the Work for both after the changes
still shows as 22.5 hours - but 21.25 ISN'T 2.73 days of 5.5 hours' duration!
I know this is probably something really fundamental about Project that I
should understand, considering I've been working with it for 6 months, but,
sad to say, I don't. I just hope that someone out there will take a look at
how long it took me to get this in here and try to give me some basic
pointers
Thanks (B-I-G thanks) in advance
Pete