Linking in combination windows

R

RoseC

Ability to link tasks within the same project using combination windows. This
would be an important feature particularly when large projects are involved.
 
M

Mike Glen

Hi Rose,

Welcome to this Microsoft Project newsgroup :)

Why not tell Microsoft ? You can submit this as a suggestion to Microsoft
at: (e-mail address removed)

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
J

John

RoseC said:
Ability to link tasks within the same project using combination windows. This
would be an important feature particularly when large projects are involved.

RoseC,
I assume you want to be able to drag a link between tasks in the
combination view much like can be done between subprojects in a master
file. However if the Predecessors field is displayed I question whether
the drag method is any easier or quicker than simply entering the Task
ID into the Predecessors field. What's the benefit?

John
Project MVP
 