Makro Problem

M

MAT

Hi..
I want to change the work of the Ressources (wiht a Makro) pro day or pro
hour.
if a task has just one ressource, i can read old-workvalue and set the new
value.
But if the task has more then one ressources, i can read the work pro day or
pro hour for each ressource but i can not change them.
Any idea for a command?
Thx...
 
J

Jan De Messemaeker

Hi MAT,

TheTask.assignments(1).ActualWork=
TheTask.assignments(2).ActualWork=

The objects to change are the Assignments belonging to the task.
HTH
 