Hi Jim/Steve,
Thanks for that. I have started with that and I will surely let you
know
if
I find any difficulties. But I am still not clear on the reply for
point
(b). I think I will expand on that :
I am handling Resource Planning and for me all the projects of the
company
are various tasks for me. Each project (or task) is for about 180 days
in
which I will need to allocate personnel. However, all personnel are
required
to be rotated/releived after a span of 45 to 60 days. How do I do that
so
that it is adequately visible in Gantt Chart.
Regards
Sudip Roy
:
Jim - equipment resources are work resources, not material. Material
resources are either a: incorporated into the deliverable being
produced -
ie, a server purchased and installed as part of a project to build a
new
network or a supply of bricks going into a wall; or b: consumed during
the
course of a task, such as fuel to run the tractors you mention.
Tractors
are neither turned over the the customer at the end of the project,
hence
are not part of the deliverable (at least not often) nor are they
consumed
by the work they do. They are just like people in that they do work,
tasks
the need them can only take place when they are otherwise free, and at
the
end of the project they stay in the inventory and can go on to other
tihngs.
If we have three tractors, our resource is a single work resource
named
"Tractor" with a max availability of 300%, meaning we can use up to
three
at
a time but not more than that.
So how do you account for the cost of the tractor? If its lifespan is
5
years of full-time use and it costs $150000, that means 150k must be
depreciated over about 10,000 working hours. 150000/10000 equals a
resource
"wage" of $15.00 per hour. The cost of using that tractor for this 40
hour
task is 40*$15 + fuel etc.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Hi Sudip -
(a) You may assign the equipment resouce (type = material) as you
wish.
If
you have several items that must be allocated (say tractors) you can
enter
separate lines. Given them a unique name Tractor1, Tractor2
(b) You can establish a resource pool and assign that pool to
mutiple
projects. The help system is pretty good on explaining it.
:
Hi!
I am Sudip. I am facing two problems
(a) I have number of equipment of same type. How do I quantify
the
number
in resource page? Do I have to type in the same material name in
that
many
rows as many equipment?
(b) I have several long projects i.e. 180 days etc where I need
to
rotate
my personnel resource in the same project. How do I do that ? and
how
can I
track the the resource utilisation?
Regards
Sudip Roy