Microsoft Project Help

J

Jennifer

How do I get the basline costs to add up all the sub tasks and the total to
be entered in the main task line. I know that I can do what I am wanting in
Excel but I want the scheduling part. i.e. Bathroom remodel, I have 5
differnet line items that I want to track the estimated cost and the actual
cost in a variance column. I want the 5 line items to add up in the Bathroom
column.
 
R

Rod Gill

Which column is the Bathroom column? If its a Cost1..Cost10 filed then
create a formula to do the sum for you.
 
S

Steve House [Project MVP]

Go to the Tools menu, Options, View tab, and in the lower right hand coender
turn on "View Project Summary Task." Then back in the Gantt chart, display
the Cost table.
 
S

Steve House [Project MVP]

In the Tools menu choose Customise, Fields. It will probably open to show
task costs 1 thru 10 but if not, switch to display them. Pick one of them
and rename it to whatever you want to call it. Toward the bottom of that
screen, you'll find some settings for how you want that new column to roll
up to the summary line.

You said you want it to roll over into the Bathroom *column." Remember that
a project WBS is organized by deliverable and its components, broken down to
their smallest logical units. Generally I would expect "Bathroom" to be a
summary task LINE, not a column and the project organization would be ...

0 Remodel House
1 Remodel Bedroom
2 Remodel Kitchen
3 Remodel Bathroom
3.1 Remove old tile
3.2 Remove old fixtures
3.3 Install new fixtures
3.3.1 Plumb new fixtures
3.4 Install new tile
3.5 Repaint walls
4 Remodel Den
..etc
..
..
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top