Two major shortcomings:
1) mpx doesn't handle time scaled data. So, if you have 10h in week1, 5h in
week2 and 15h in week 3, then the mpx format exports 10h per week for 3
weeks. It also doesn't export any fields added to Project from 2000 onwards.

2) mpx is no longer supported. The replacement is xml. Project 2002 onwards
can export and import xml files. Xml files support all fields up to and
including 2003.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 