How can I compare actual progress to Baseline1 saved in MS Project 2003?

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...ae95-164a345a0216&dg=microsoft.public.project
 
R

Rod Gill

Hi,

View, More Views
Copy the Tracking Gantt chart and call it Tracking Baseline1
OK, Apply
Format, Bar Styles
Edit the Baseline style to use Baseline1 dates
OK

This view should now do what you want.
 