MS Project & multiple task relationships

W

William Ibbs

I would like to see MS Project be able to accomodate 2 or more relationships.
Such as Start-to-start and Finish-to-Finish.

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...b6e6-6fd5884d0931&dg=microsoft.public.project
 
J

John

William Ibbs said:
I would like to see MS Project be able to accomodate 2 or more relationships.
Such as Start-to-start and Finish-to-Finish.

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/community/en-us/default.mspx?mid=3c51d51b-ce5f
-4824-b6e6-6fd5884d0931&dg=microsoft.public.project

William,
Just for your reference, a hammock task effectively emulates the
start-to-start and a finish-to-finish on a single task. For more
information, go to our MVP website
at:http://www.mvps.org/project/faqs.htm
and look at FAQ 19 - Hammock Task

Hope this helps.
John
Project MVP
 
D

Dean C

When you create a hammock, be sure that the task type is not "Fixed
Duration", or it will not work.
 