THIS MESSAGE IS RESENT BECAUSE I AM NOT CERTAIN THE FIRST ONE WENT THROUGH. IF IT DID, PLEASE EXCUSE ME
I have a problem linking timephased resource data from Project 2002 to Excel. I have followed some of the messages on the newsgroup, but I need further guidance
The "Analyse Time scaled data in Excel" tool does not work for transferring material quantities. I can copy and paste the data, but this is not acceptable, prone to error. It does not appear possible to link the timephased data to Excel, as you can with the data tables
It seems that I need a customized macro that will select the data from the materials usage time phased sheet, open an Excel file, and paste the data line by line so that I can allocate the data using another macro
I trust you will be able to assist .
Incidentally, I went to Jack Dahlgren home page, which I got from this group, and tried to contact him, but the email address on his home page does not respond. Can you provide a correct contac
Desmond Mallalieu
THIS MESSAGE IS RESENT BECAUSE I AM NOT CERTAIN THE FIRST ONE WENT THROUGH. IF IT DID, PLEASE EXCUSE ME
I have a problem linking timephased resource data from Project 2002 to Excel. I have followed some of the messages on the newsgroup, but I need further guidance
The "Analyse Time scaled data in Excel" tool does not work for transferring material quantities. I can copy and paste the data, but this is not acceptable, prone to error. It does not appear possible to link the timephased data to Excel, as you can with the data tables
It seems that I need a customized macro that will select the data from the materials usage time phased sheet, open an Excel file, and paste the data line by line so that I can allocate the data using another macro
I trust you will be able to assist .
Incidentally, I went to Jack Dahlgren home page, which I got from this group, and tried to contact him, but the email address on his home page does not respond. Can you provide a correct contac
Desmond Mallalieu