Hi MichealK,
To Unlink:
Double click on the Project Summary task for the subproject to show the
Insert Project Information dialog box. Click the advanced tab and
remove the check from Link to project check box.
To Delete:
Click the row number, press the delete key. A message about "summary
tasks" will appear. Choose Continue and click OK.
If you have difficulty deleting the inserted project, check the Service
Pack you are using for MS Project 2003. (Help > About Microsoft Project
Office. If you are not running SP-1 this could explain any
difficulties.
I hope this helps. Let us know how you get along.
Julie