Project 2007 - Set Project Priority

M

miamione

In 2003 you can set the project's priority through Project/Project
Information and then entering the priority in the pop up window. In 2007
there is no field in the pop up window to enter the project priority. Where
can it be entered?
 
J

JulieS

Hi Miamione,

Hmm....when I display the Project Information dialog box through Project
Project Information, there is a priority field under the calendar
drop-down list.

Are you using the released version ?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
M

miamione

I downloaded the trial version. There is no field labeled Priority under the
field labeled Calendar as exists in 2003. Perhaps when I buy the software
the field will appear?
 
J

Jim Aksel

Mine shows the same as Julie, full retail version of P2007 Professional.
Additionally, priorities for specific tasks are available in the Task
Information dialog on the General Tab.
 
M

miamione

I was able to confirm with a coworker that the fully licensed version of 2007
does have this capability, but the 30 day trial version has this error.
 