Project ressource pool

S

Stian

When I have entered reoccuring task's for example 3 hours an intere week. My
ressource pool shows that the ressource is fully booked the entire day, exept
the last where it correctly states 3 hours. What have I done wrong ???
 
G

Gérard Ducouret

Hello Stian,
It works fine for me. Could you tell us step by step how did you create the
reccurent tasks and assignments ?

Gérard Ducouret
 
S

Stian

Step by step. "Insert" -> "Reccuring task" -> write task name -> set duration
to 3h -> select "daily" -> select "workday" -> set start and end date ->
select the standard calender for the project (where worktime is set to 6,5
hours). Then save and "yes" to update ressource pool.
 
G

Gérard Ducouret

Stian,
I can't reproduce the trick. Did you check that the ressource is not
assigned on another task during this periode?
NB : The standard calendar is not usefull in this dialog box if it's exactly
the Standard Project calendar.

Gérard Ducouret
 
S

Stian

The calender is one I have produced. No the resources are not booked by other
task's. Also it states in the ressourcepool that the specific task is taking
6,5 hours (Full work day)
 
G

Gérard Ducouret

Stian,
Could you send me the project file?
My address is ducouret dot gerard at free dot fr

Gérard
 
G

Gérard Ducouret

Stian,
The solution is quite simple :
The problem comes from the fact that you assigned each resource twice :
- On each elementary task (task's OK)
- On the summary of elementary task (That's too bad !)
What version of project are you using ? Normally, 2003 avois this kind of
problem...
So :
Select a summary of reccurent task (which has a small + sign)
In the Assign Resource dialog, select the resource and click Remove.

Gérard Ducouret
 