Dear All
I am new to the Project Server 2003. I need to migrate the existing Project
Server 2003 installation to a new computer with all its data and
configuration intact.Please let me know the steps
thanx a lot
 
G

Gizmo Gizmo

Hi,
it could be as simple as to:
1. Backup the Project server database on first server
2. Install PS on the second server, get it up and running.
3. Restore the database to the second server.
4. You will have to re-create MSProjectServerUser and MSProjectUser. For
further info see: http://support.microsoft.com/default.aspx/kb/323330
5. Enter the settings for Project to access the database eighter in EditSite
utility or ConnInfo.exe (in project \bin folder)

If you are using sharepoint workspaces etc and want to migrate those as well
things get more complicated and I am afraid I can't help you on this.