P
P
Hi,
i am trying to allocate material resources to milestones to indicate costs
being incurred when items are received.
MSP won't let me do this without increasing the task duration to >0, hence
no longer a true milestone and padding my schedule. Is there any way to
force materials onto 0-lengths activities?
thanks,
P.
i am trying to allocate material resources to milestones to indicate costs
being incurred when items are received.
MSP won't let me do this without increasing the task duration to >0, hence
no longer a true milestone and padding my schedule. Is there any way to
force materials onto 0-lengths activities?
thanks,
P.