Hi Julie.
Thanks for responding. What I mean is this: For example, I have a project
plan with 50 tasks. At this point, I have closed 20 of them. Meaning the
work on those have been completed, and the tasks are closed at 100% complete.
Now I'm at the point of rebaselining my entire plan. When I go through the
steps of baselining the entire project (tools, tracking, save baseline,
entire project), a portion of those prior closed tasks open up. Meaning,
they switch from 100% complete to 0% complete.
I'm trying to find out what could possibly open up closed tasks by simply
rebaselining those tasks. I use MSP 2003. I need to speak with my LAN group
to determine if we have all the SP's. I was thinking it was possibly a
setting in the options I am overlooking, and that someone has seen this same
issue and knew the fix. I can't find it in any documentation up to date.
Thanks for your help and let me know if you hear or find anything.
Dave