Hi there - MS Project 2003 Newbie needing help!
I have a task with the following time requirements:
- August 11.25 hours
- September 5 hours
- October 5 hours
- November 5 hours
- December 10 hours
- January 10 hours
I would like to see only ONE task.
And I will divide the required monthly hours by week (ie. Sep = 5 hours,
would like to see 1.25 hours/week)
What is the best way to do this?
I've looked at splitting a task as well as the recurring task features.
Is there an easier way??
Appreciate your help!
I have a task with the following time requirements:
- August 11.25 hours
- September 5 hours
- October 5 hours
- November 5 hours
- December 10 hours
- January 10 hours
I would like to see only ONE task.
And I will divide the required monthly hours by week (ie. Sep = 5 hours,
would like to see 1.25 hours/week)
What is the best way to do this?
I've looked at splitting a task as well as the recurring task features.
Is there an easier way??
Appreciate your help!