When I set up a recurring task to occur every Wednesday, the first one always
starts on Monday and then the rest are on Wed. How can I fix this so that
all of them are on Wed?
 
J

Jim Aksel

I cannot duplicate this behavior. Please make sure you have installed the
latest service packs and updates and try again. The latest is SP3 for
Project 2003.
Post back if you still have trouble
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
N

New_Project_User

I noticed that I had the tasks indented farther than necessary. Once I
decreased the indent, that also fixed the start day issue.

I have Project 2002 and I will try to download the latest SP. Thank you for
trying to recreate my problem and also for sending me the link to the MVP
website. I've added it to my favorites!
 