Resource Rate - Escalated Table

A

Aviator

Dear Sir (or Madam);
Contracting to the government involves planning labor rates, under two
circumstances: ON-SITE vs OFF-SITE, over an esclation schedule. For example;

ON-SITE ($/hr) | 2004| 2005| 2006| 2007|2008 etc..
Engineering Scientist |59.80|61.60|63.44|65.34|67.31|...
Engineering Technician |24.84|27.81|25.59|26.35|27.14|...
etc.

OFF-SITE ($/hr) | 2004| 2005| 2006| 2007|2008 etc..
Engineering Scientist |65.00|66.95|68.95|71.02|73.15|...
Engineering Technician |27.00|27.81|28.64|29.50|30.39|...
etc.

These Resource Rate data presently exist in an Excel spreadsheet. Question:
What's the best way to import this kind of resource info into Ms. Project?...
 
J

John

Aviator said:
Dear Sir (or Madam);
Contracting to the government involves planning labor rates, under two
circumstances: ON-SITE vs OFF-SITE, over an esclation schedule. For example;

ON-SITE ($/hr) | 2004| 2005| 2006| 2007|2008 etc..
Engineering Scientist |59.80|61.60|63.44|65.34|67.31|...
Engineering Technician |24.84|27.81|25.59|26.35|27.14|...
etc.

OFF-SITE ($/hr) | 2004| 2005| 2006| 2007|2008 etc..
Engineering Scientist |65.00|66.95|68.95|71.02|73.15|...
Engineering Technician |27.00|27.81|28.64|29.50|30.39|...
etc.

These Resource Rate data presently exist in an Excel spreadsheet. Question:
What's the best way to import this kind of resource info into Ms. Project?...

Aviator,
Your question is nearly identical to one asked last week in this
newsgroup. Use a search and look for the post, "Import resource cost
data" by Jenn on Oct 26, 2005.

Hope this helps.
John
Project MVP
 
Top